Blame

aa4ad9 Anonymous 2026-09-08 15:40:03
Publish dated owner progress board
1
# Hold The Horde — Progress
2
a05728 Anonymous 2026-09-09 18:53:39
Record both proposal submissions and active review; link the new reading path
3
**Work resumed on 9 September 2026. Updated 18:53 Jerusalem.** The team is correcting the game direction following the owner's review. Automatic PM checks are active.
474440 Anonymous 2026-09-09 13:05:20
Owner570 feedback pause; preserve completed first-pass564 and stopped drafts
4
242490 Anonymous 2026-09-09 18:39:17
Resume owner-directed correction; replace obsolete status layers with current plan and forecast
5
The next owner delivery is a revised pitch, an expedition with convincing horde pressure and discovery, and three spectacular build examples. It must address all three blockers: survivorslike scale and urgency, human-readable explanations, and concrete reasons for fun, challenge and emotional payoff.
474440 Anonymous 2026-09-09 13:05:20
Owner570 feedback pause; preserve completed first-pass564 and stopped drafts
6
242490 Anonymous 2026-09-09 18:39:17
Resume owner-directed correction; replace obsolete status layers with current plan and forecast
7
## Current work
3f5678 Anonymous 2026-09-08 15:56:59
Add milestone forecast F1, target dates, staffing and uncertainty
8
242490 Anonymous 2026-09-09 18:39:17
Resume owner-directed correction; replace obsolete status layers with current plan and forecast
9
| Task | Owner | Status | Target, Jerusalem |
10
|---|---|---|---|
a05728 Anonymous 2026-09-09 18:53:39
Record both proposal submissions and active review; link the new reading path
11
| 41 — [Hordes and three builds](/Hold%20The%20Flood/Hordes%20and%20Builds) | Systems | Submitted at 18:48; PM read | In combined review |
12
| 42 — [Revised pitch and expedition](/Hold%20The%20Flood/The%20Game) | Design Lead | Submitted at 18:40; PM read, corrections needed | First draft delivered early; response follows combined review |
13
| 43 — Independent review | Reviewer | Reviewing both drafts; start confirmed at 18:52 | Today 19:50; range 19:35–20:10 |
242490 Anonymous 2026-09-09 18:39:17
Resume owner-directed correction; replace obsolete status layers with current plan and forecast
14
| 38 — Design readiness | PM | Reopened; awaits correction and owner reaction | First-pass revision target 15 September |
15
| 39–40 — Earlier mechanism/discovery details | Systems / Lead | Parked, unaccepted drafts | Reassess after the new direction |
16
| Clear wiki navigation and current reports | PM | In progress; reading map prepared | Alongside the corrected proposal |
49369b Anonymous 2026-09-08 16:27:44
PM forecast F1.2: actual outline completion and next scoped deliveries
17
a05728 Anonymous 2026-09-09 18:53:39
Record both proposal submissions and active review; link the new reading path
18
**43 tracked design outcomes: 37 preparation-closed, 1 reopened readiness outcome, 2 parked drafts, 3 assigned correction outcomes.** All three roles have confirmed receipt: Both authors have submitted and stopped; the Reviewer is examining the two drafts against independently saved criteria. Both proposals remain unaccepted. These counts describe writing and review outcomes, not the percentage of the game complete. The temporary wiki assistant's reading map is PM support, not another design outcome or permanent role.
3f5678 Anonymous 2026-09-08 15:56:59
Add milestone forecast F1, target dates, staffing and uncertainty
19
242490 Anonymous 2026-09-09 18:39:17
Resume owner-directed correction; replace obsolete status layers with current plan and forecast
20
## Forecast
aa4ad9 Anonymous 2026-09-08 15:40:03
Publish dated owner progress board
21
242490 Anonymous 2026-09-09 18:39:17
Resume owner-directed correction; replace obsolete status layers with current plan and forecast
22
| Milestone | Working target | Plausible window | Dependency |
23
|---|---|---|---|
24
| Corrected proposal for owner reaction | 10 September, 18:00 | This evening–10 September evening | Both drafts, one focused critique and a bounded response |
25
| Readable, coherent first-pass design wiki | 15 September | 13–17 September | Owner reaction to the direction; approximately 2–4 further working days of revision |
26
| Detailed campaign design | 17 November | 27 October–15 December | Selected direction and a fresh estimate of the resulting content/detail work |
4904fc Anonymous 2026-09-08 20:59:08
Record Story30 closure and Cast31 submission/review; forecast F1.12
27
242490 Anonymous 2026-09-09 18:39:17
Resume owner-directed correction; replace obsolete status layers with current plan and forecast
28
Confidence is low for the first two targets and very low for detailed campaign design. Dates assume the existing three roles and PM remain available, approximately 6–8 active hours per working day, and consequential owner feedback within a working day. An earlier useful proposal will be delivered immediately. These are design estimates; development has a separate authorization and schedule.
287b77 Anonymous 2026-09-08 19:11:18
Record acquisition closeout, combat roster work and revised coverage
29
242490 Anonymous 2026-09-09 18:39:17
Resume owner-directed correction; replace obsolete status layers with current plan and forecast
30
| Phase | 9 Sep | 10 Sep | 13–17 Sep | Following weeks |
31
|---|---|---|---|---|
32
| Pitch, horde rhythm and build examples | Draft | Review / owner reaction | | |
33
| Rewrite the main reading path | Structure | Begin after direction | Revise / integrate | |
34
| Detailed campaign specification | Parked | Parked | Re-estimate | Resume selected detail work |
db6396 Anonymous 2026-09-09 10:45:05
PM: resume team, record33 closure and499 submissions; adopt dated F1.14 forecast
35
a05728 Anonymous 2026-09-09 18:53:39
Record both proposal submissions and active review; link the new reading path
36
**What changed:** the earlier 9 September readiness declaration was withdrawn after the owner's three critical objections. Both first drafts arrived ahead of the 19:15 target; the review target has moved from20:15 to19:50. The old 10 November detailed-design target has moved to a provisional 17 November and its range widened to allow for mechanical and content rework. This extra allowance is a planning judgment, not measured remaining effort. Previous forecasts remain in page history and the PM forecast checkpoint.
aa4ad9 Anonymous 2026-09-08 15:40:03
Publish dated owner progress board
37
242490 Anonymous 2026-09-09 18:39:17
Resume owner-directed correction; replace obsolete status layers with current plan and forecast
38
Read the [Design Plan](/Hold%20The%20Flood/Design%20Plan) for the correction's acceptance criteria and [Design Coverage](/Hold%20The%20Flood/Design%20Coverage) for the affected areas. [Design readiness](/Hold%20The%20Flood/V1%20Readiness) remains open. The five earlier unanswered owner choices remain unresolved; they do not prevent this correction work.