Hold The Horde — Progress

Work resumed on 9 September 2026. Updated 18:53 Jerusalem. The team is correcting the game direction following the owner's review. Automatic PM checks are active.

The next owner delivery is a revised pitch, an expedition with convincing horde pressure and discovery, and three spectacular build examples. It must address all three blockers: survivorslike scale and urgency, human-readable explanations, and concrete reasons for fun, challenge and emotional payoff.

Current work

Task Owner Status Target, Jerusalem
41 — Hordes and three builds Systems Submitted at 18:48; PM read In combined review
42 — Revised pitch and expedition Design Lead Submitted at 18:40; PM read, corrections needed First draft delivered early; response follows combined review
43 — Independent review Reviewer Reviewing both drafts; start confirmed at 18:52 Today 19:50; range 19:35–20:10
38 — Design readiness PM Reopened; awaits correction and owner reaction First-pass revision target 15 September
39–40 — Earlier mechanism/discovery details Systems / Lead Parked, unaccepted drafts Reassess after the new direction
Clear wiki navigation and current reports PM In progress; reading map prepared Alongside the corrected proposal

43 tracked design outcomes: 37 preparation-closed, 1 reopened readiness outcome, 2 parked drafts, 3 assigned correction outcomes. All three roles have confirmed receipt: Both authors have submitted and stopped; the Reviewer is examining the two drafts against independently saved criteria. Both proposals remain unaccepted. These counts describe writing and review outcomes, not the percentage of the game complete. The temporary wiki assistant's reading map is PM support, not another design outcome or permanent role.

Forecast

Milestone Working target Plausible window Dependency
Corrected proposal for owner reaction 10 September, 18:00 This evening–10 September evening Both drafts, one focused critique and a bounded response
Readable, coherent first-pass design wiki 15 September 13–17 September Owner reaction to the direction; approximately 2–4 further working days of revision
Detailed campaign design 17 November 27 October–15 December Selected direction and a fresh estimate of the resulting content/detail work

Confidence is low for the first two targets and very low for detailed campaign design. Dates assume the existing three roles and PM remain available, approximately 6–8 active hours per working day, and consequential owner feedback within a working day. An earlier useful proposal will be delivered immediately. These are design estimates; development has a separate authorization and schedule.

Phase 9 Sep 10 Sep 13–17 Sep Following weeks
Pitch, horde rhythm and build examples Draft Review / owner reaction
Rewrite the main reading path Structure Begin after direction Revise / integrate
Detailed campaign specification Parked Parked Re-estimate Resume selected detail work

What changed: the earlier 9 September readiness declaration was withdrawn after the owner's three critical objections. Both first drafts arrived ahead of the 19:15 target; the review target has moved from20:15 to19:50. The old 10 November detailed-design target has moved to a provisional 17 November and its range widened to allow for mechanical and content rework. This extra allowance is a planning judgment, not measured remaining effort. Previous forecasts remain in page history and the PM forecast checkpoint.

Read the Design Plan for the correction's acceptance criteria and Design Coverage for the affected areas. Design readiness remains open. The five earlier unanswered owner choices remain unresolved; they do not prevent this correction work.