**Paused for human feedback — 2026-09-09 13:05 Jerusalem.** The owner requested this checkpoint after first-pass completion. All design workers are stopped: Reviewer572, Systems573 and Design Lead574 confirm no work/write in flight. Automatic PM checks are PAUSED. Resume requires an explicit owner instruction; earlier assignments and forecast dates do not restart work.
+
+
**40 tracked outcomes: 38 preparation-closed, 2 paused, 0 active.** The complete first-pass batch is38/38 closed. M2 coherent core and M3 complete first-pass wiki were achieved on9 September at12:51:39 after [V1 Readiness](/Hold%20The%20Flood/V1%20Readiness) disposition564 and verified source repairs. All15 major domains have first-pass coverage; this is not a percentage of the finished game or approval of every provisional choice.
+
+
| Outcome | Current state | Next action after feedback and explicit resumption |
+
|---|---|---|
+
|38 — Whole-wiki readiness|Closed564; M2/M3 achieved|Use the first-pass baseline for human review|
+
|39 — [Opening Mechanism Detail](/Hold%20The%20Flood/Opening%20Mechanism%20Detail)|Paused, unaccepted draft submitted569; Systems stopped573|PM reads the actual draft; then one focused critique/response if still wanted|
+
|40 — [Paired Transfer Discovery Detail](/Hold%20The%20Flood/Paired%20Transfer%20Discovery%20Detail)|Paused, unaccepted draft submitted568; Lead stopped574|PM reads the actual draft; then one focused critique/response if still wanted|
+
|Reviewer criteria for39/40|Saved571 before either draft; Reviewer stopped572 without starting a critique|Preserve the criteria; do not review while paused|
+
+
The two detailed drafts arrived just before the pause and have not been accepted. Their new text, occurrences, quantities or refinements do not amend the first-pass baseline. No further source integration, design authoring or review is scheduled during the hold. The five outstanding owner choices remain unanswered; existing proposals and the early story draft remain revisable.
+
+
**Forecast status.** F1.15 records actual M2/M3 completion on9 September, replacing F1.14's predicted11/14 September dates. There is no remaining M3 task or forward10–18-hour coherence allowance. The previous detailed-campaign estimate was10 November (20 October–1 December), low confidence; it and the same-day39/40 targets are now **on hold**, to be rebased after feedback/resumption. Paused time is not counted as agent work. No additional agent or implementation phase is required for the human review.
+
+
All work remains design only. No code, build, simulation, playtest, purchase or game asset is authorized by first-pass completion or this pause.
+
+
## Historical record through message560
+
+
The following is retained unchanged apart from heading depth as a dated record. Its old current-status, ownership, remaining-work and scheduling statements are superseded by the pause and completion record above; they are not active instructions. Detailed F1–F1.14 forecasts and earlier deliveries remain available here.
+
+
## Hold The Horde — Progress
+
**Updated 2026-09-09 12:40 Jerusalem (UTC+3); current status through560.** The owner resumed all project work and original Claude roles in490. All work remains **design only**.
**38 tracked design packages:37 preparation-closed,1 open (38).** Scope and development handoff refresh37 ([Production Scope](/Hold%20The%20Flood/Production%20Scope); [Development And Validation Handoff](/Hold%20The%20Flood/Development%20And%20Validation%20Handoff)) closed550 at12:05:47. [V1 Readiness38](/Hold%20The%20Flood/V1%20Readiness), assigned551–553, gives a stable ID to the already-planned final coherence/readiness work; it adds no game scope. All15 domains have usable first-pass contracts/0 partial; M2/M3 are not yet declared complete and this is not a game-completion percentage. Existing24 modules/40 rooms,12 equipment definitions,10 encounters INCLUDING2 setpieces and13 major mechanisms remain proposed content;13 is not every interactive object. Intake407 and administration add no further packages.
@@ 10,7 33,7 @@
**Actual availability and handoffs:** original identities/models/efforts remain unchanged. Lead560 is WORKING on the ONE response to critique559, incorporating the submitted557 assessment and555 factual audit. Receiving was verified at12:35:14.291 Jerusalem and the full559/560 reading at12:35:31.379; one courier was delivered. Reviewer is STOPPED after559; Systems remains STOPPED after555. Lead owns only the administrative V1 Readiness article. PM is preparing bounded local parent repairs; game sources remain unchanged and no parent ownership transfer is implied. All existing game articles and prior parent ownership are STOPPED; no37 follow-up is authorized. PM owns36/Home/Information STOPPED. No additional permanent agent or owner forwarding is needed.
-
## Forward forecast — baseline F1
+
### Forward forecast — baseline F1
**Adopted F1.14 forecast — 9 September:** M3 first-pass wiki now targets **14 September (11–18 September), low confidence**. M2 coherent core remains11 September (10–14); M4 detailed campaign remains10 November (20 October–1 December). Earlier published22 September remains in the history below. These are estimates, not deadlines guaranteed by team agreement.
@@ 30,7 53,7 @@
M4 remains a low-confidence forecast: the SMALL inventory is prepared but not an owner-selected final game size, and exhaustive branch/arrangement depth is unproven. Scope37 supplies a current conditional350–590 role-hour M4 roll-up; it does not count uncreated specialists as available capacity. The initial30–60-working-day estimate with two additional specialists, and40–80 with the original team alone, are historical baseline scenarios rather than current staffing prerequisites. The10November target (20October–1December) remains unchanged pending actual evidence. Re-estimate after three representative detailed packages—a mechanism room, a two-language correction and a short rescue/home arc—are written and checked. Final gameplay validation requires a separately authorized phase and has no established endpoint.
-
## Estimated work timeline
+
### Estimated work timeline
This is a planning schedule, not historical delivery data. “Buffer” is allowed revision/decision time, not an unassigned promise to polish indefinitely.
@@ 47,7 70,7 @@
**Adopted F1.14 forecast — 9 September:** M3 first-pass wiki now targets **14 September (11–18 September), low confidence**. M2 coherent core remains11 September (10–14); M4 detailed campaign remains10 November (20 October–1 December). The revision follows the remaining-deliverables audit and preparation closeouts25–33, including the actual24-module/40-room and ten-encounter/thirteen-mechanism first passes. It uses current PM, Systems and restored original Lead/Reviewer capacity; additional agents are not prerequisites. It is a scope-based calendar judgment, not a conversion of word counts or elapsed chat minutes into role-hours. A changed joining architecture, expanded first-pass scope, unresolved integration or unavailable capacity can move the estimate. Next scheduled re-estimate:9 September18:00 Jerusalem, or sooner after consequential acceptance, scope or capacity changes. The earlier absent-two-specialists→25Sep scenario is historical and no longer the current schedule. The earlier14Sep conditional calculation in yesterday’s unpublished draft is now explicitly adopted by PM.
-
## Extra agents — when and why
+
### Extra agents — when and why
**No extra agent creation is required today.** Restored original Lead/Reviewer and existing Systems have substantive parallel assignments. Reconsider a technical/production specialist on10 September only if the concrete handoff queue needs independent expertise; campaign evidence integration is optional only for an actual unresolved gap.
@@ 60,7 83,7 @@
The original staffing proposal preceded accepted regional, language, story, cast, room and encounter inventories. Do not duplicate campaign maps or chains to occupy a role. Specialist absence no longer automatically implies a25 September wiki target; the adopted14 September estimate uses the restored existing team.
-
## Why these estimates, and when they change
+
### Why these estimates, and when they change
The revision follows the remaining-deliverables audit and preparation closeouts25–33, including the actual24-module/40-room and ten-encounter/thirteen-mechanism first passes. It uses current PM, Systems and restored original Lead/Reviewer capacity; additional agents are not prerequisites. It is a scope-based calendar judgment, not a conversion of word counts or elapsed chat minutes into role-hours. A changed joining architecture, expanded first-pass scope, unresolved integration or unavailable capacity can move the estimate. Historical early2–4/6–12/8–15/30–60-day allowances remain dated planning hypotheses; no new labor balance is inferred from them.
@@ 89,7 112,7 @@
|F1.13|8 Sep21:22|Cast31 actual closeout473 at21:12:44 recorded against its22:30 reviewed target(22:00–23:30); initial draft470 arrived20:53:50. Station Room And Module Inventory32 assigned475, native receiving verified21:13:24.363; draft477 submitted21:22:49 at15bb8454 before23:00 on8Sep(22:15 on8Sep–00:00 on9Sep). Systems STOPPED; one review active under476. Reviewed00:00 on9Sep(23:15 on8Sep–01:15 on9Sep) remains the low-medium-confidence forecast. Cast is now usable first-pass, bringing coverage to13usable/2partial; room/module and full encounter/mechanism inventories remain unfinished. Global04, M2–M4, planned9–10Sep staffing, the current-team scenario and dated144–247 allowance caveat remain unchanged.|
|F1.14|9 Sep 10:45|Owner resumed all roles490 after authorized overnight downtime. Room32 closed481 on8Sep21:44:18; Encounter33 closed493 on9Sep10:32:09, final5c1a9ad6, after one critique/response and narrow PM integration492.34 information assigned491; global04 assigned494; original Reviewer preauthorized495. Current34 tracked/32 closed/2 open;14 usable/1 partial. PM adopts M3 **14Sep (11–18), low confidence**, from remaining-scope audit and accepted25–33 with the restored team; no extra agents prerequisite.04/34 drafts9Sep12:00 (11:15–12:45), reviewed13:00 (12–14), low-medium. M2/M4 unchanged. Night pause is not a failed deadline. Earlier Sep22 and missing-two-specialists→Sep25 scenarios remain historical. Yesterday’s F1.14 draft was local and unpublished; this row is the new adoption record. Dated144–247 allowance is not current remaining labor.|
-
## Delivery history and current changes
+
### Delivery history and current changes
- [Combat And Enemy Roster27](/Hold%20The%20Flood/Combat%20And%20Enemy%20Roster) preparation-closed443 at19:34, finalf1fe0d9a. One focused review/response corrected the new-role triggers and counterplay, staged cues for both regional orders, and Bellback's warning-start cone lock. Six ordinary/three special roles and two setpieces are prepared within ten encounter placements; exact populations, geometry, presentation and tuning remain later work.
- [Home And Colony Loop28](/Hold%20The%20Flood/Home%20And%20Colony%20Loop) preparation-closed450 at20:01:12, final5bff3436. One focused review/response clarified shared commissioning, first-return actions and each project's participants and lasting facilities. Five project briefs remain two reused/three new with three new fixed ship fixtures; cast choices, full scene scripts/state variants and management economy remain separate; Cast31 first-pass allocation is now prepared473.
@@ 109,7 132,7 @@
- [V1 Readiness38](/Hold%20The%20Flood/V1%20Readiness) assigned551–553 for the existing final coherence/readiness obligation. Lead560 is WORKING on the ONE response to critique559, incorporating the submitted557 assessment and555 factual audit. Receiving was verified at12:35:14.291 Jerusalem and the full559/560 reading at12:35:31.379; one courier was delivered. Reviewer is STOPPED after559; Systems remains STOPPED after555. Lead owns only the administrative V1 Readiness article. PM is preparing bounded local parent repairs; game sources remain unchanged and no parent ownership transfer is implied. Response13:15 (12:50–14:00), reviewed16:00 (14:30–18:00); no new game content or scope.
- Five unanswered owner questions and unadopted intake407 remain. All original roles resumed490. M3 now targets14 September (11–18), low confidence; M2/M4 remain unchanged. The144–247 allowance remains dated. Yesterday’s F1.14 drafts were not published.
-
## Open and closed outcomes
+
### Open and closed outcomes
All milestone times below are Jerusalem time. “Updated” separates later owner-rule integration from the original preparation closeout.
@@ 154,7 177,7 @@
|37|Scope and development handoff refresh37 ([Production Scope](/Hold%20The%20Flood/Production%20Scope); [Development And Validation Handoff](/Hold%20The%20Flood/Development%20And%20Validation%20Handoff))|Closed|Reviewed scope/packet planning proposal; no development authority|9Sep12:05:47 closeout550; response54911:58:19; final68db46ea/59945901|ONE critique/response and exact factual verification.21,243/27,529 bytes; both Systems STOPPED. Prior15:00 reviewed target achieved; only10–18 coherence role-hours remains forward|
|38|[V1 Readiness38](/Hold%20The%20Flood/V1%20Readiness)|Open — ONE response560 underway|Previously planned final coherence/readiness assessment and supporting audit; no new game scope|Lead560 WORKING on ONE response; Reviewer STOPPED559; Systems STOPPED555; receiving/full reading verified|Response13:15 (12:50–14:00), reviewed16:00 (14:30–18). PM prepares bounded local parent repairs and decides M2/M3; sources remain unchanged|
-
## Recent delivery timeline
+
### Recent delivery timeline
These are observed calendar spans from assignment to preparation closeout, including handoffs and review. They are historical measurements, not estimates of labour or promised future turnaround.
Current ownership through560: Lead owns only the administrative V1 Readiness article and is WORKING on the ONE response560. Systems552 local factual support was submitted555; Systems is STOPPED and holds no new article ownership. Reviewer553 criteria554 and ONE critique559 are complete; Reviewer is STOPPED. PM prepares bounded local parent repairs, with no shared source change or ownership transfer from draft work. Existing game articles retain their STOPPED owners, including Systems’ two37 parents, Mechanical35 and ten mechanical parents; PM36/Home/Information remain STOPPED. Any actual parent repair requires explicit transfer.
-
## Decisions for the owner
+
### Decisions for the owner
**Already answered:** opening A and persistent room/group connections across shifts, culminating in connecting the entire station.
@@ 212,6 235,6 @@
**New rescue question now with the owner (485):** if the astronaut dies during an eligible short rescue, use a protected retreat that leaves the survivor alive and unsent in the prepared refuge before one shift, with spent supplies still spent and a new short route to find; or allow danger and prepare concrete injury/loss options for a later choice. The proposed protection is new and unselected. No answer is inferred; the earlier four questions remain pending, making five.
-
## Reporting agreement
+
### Reporting agreement
PM sends a compact report every15 minutes during authorized active work, plus meaningful completion, disagreement, blocker or decision updates. Owner pause suspends work/check-ins;490 explicitly resumed them. Reports include open/closed preparation counts, actual delivery/activity, next target/range, current v1 forecast and its changes. No page/message count or invented game-completion percentage substitutes for progress. The fallback requires the computer and apps to remain available.