Blame

aa4ad9 Anonymous 2026-09-08 15:40:03
Publish dated owner progress board
1
# Hold The Horde — Progress
2
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
3
**Paused for owner feedback. Updated 9 September 2026.** All three workers and automatic PM checks remain stopped. Design readiness has been reopened following the owner's review.
474440 Anonymous 2026-09-09 13:05:20
Owner570 feedback pause; preserve completed first-pass564 and stopped drafts
4
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
5
The owner identified three blocking problems:
474440 Anonymous 2026-09-09 13:05:20
Owner570 feedback pause; preserve completed first-pass564 and stopped drafts
6
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
7
1. **Genre and scale:** the described encounters, builds and pacing do not deliver a survivorslike with hordes, spectacle and urgency.
8
2. **Readable design:** the wiki is hard for a human to navigate and understand, with scattered explanations, unexplained references, old discussions and excessive qualifications.
9
3. **Player experience:** the design rarely explains what makes an event fun, exciting or challenging, how pressure and climaxes develop, or what the player is expected to feel and why.
3f5678 Anonymous 2026-09-08 15:56:59
Add milestone forecast F1, target dates, staffing and uncertainty
10
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
11
The PM accepts these as failures of the current design and its review standard. Consistency and coverage checks were insufficient grounds for declaring readiness. The earlier closure is a historical preparation milestone; the game direction and wiki now require correction.
49369b Anonymous 2026-09-08 16:27:44
PM forecast F1.2: actual outline completion and next scoped deliveries
12
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
13
**40 tracked outcomes: 37 preparation-closed, 1 reopened, 2 paused drafts, 0 active.** Earlier completed work remains available for reuse; this count measures documents and reviews, not game quality or percentage complete.
3f5678 Anonymous 2026-09-08 15:56:59
Add milestone forecast F1, target dates, staffing and uncertainty
14
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
15
| Outcome | Current state | Next step |
3f5678 Anonymous 2026-09-08 15:56:59
Add milestone forecast F1, target dates, staffing and uncertainty
16
|---|---|---|
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
17
| 38 — [Design readiness](/Hold%20The%20Flood/V1%20Readiness) | Reopened; M2 core and M3 first-pass wiki acceptance withdrawn | Resolve the three owner blockers before declaring readiness again |
18
| 39 — [Opening Mechanism Detail](/Hold%20The%20Flood/Opening%20Mechanism%20Detail) | Paused; submitted draft, unaccepted | Reassess whether its direction is useful after correction |
19
| 40 — [Paired Transfer Discovery Detail](/Hold%20The%20Flood/Paired%20Transfer%20Discovery%20Detail) | Paused; submitted draft, unaccepted | Reassess whether its direction is useful after correction |
aa4ad9 Anonymous 2026-09-08 15:40:03
Publish dated owner progress board
20
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
21
**Proposed next delivery after explicit resumption:** a short revised pitch, one expedition showing pressure and release, three spectacular build examples, and a clear reading structure for the wiki. These are proposals for owner reaction before further detailed specification. No new assignment has been dispatched.
4904fc Anonymous 2026-09-08 20:59:08
Record Story30 closure and Cast31 submission/review; forecast F1.12
22
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
23
**Rough forecast:** one active working day for that correction proposal, then an estimated 2–4 additional working days for a readable first-pass revision after the owner selects the direction. Confidence is low; this estimates a coherent first pass, not exhaustive campaign detail. The team is paused, so no calendar deadline is running. Re-estimate after the proposal establishes how much mechanics/content must change. The previous detailed-campaign target of 10 November (20 October–1 December) is suspended and no longer a reliable baseline following this feedback.
287b77 Anonymous 2026-09-08 19:11:18
Record acquisition closeout, combat roster work and revised coverage
24
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
25
The owner-confirmed brief remains authoritative. The five earlier unanswered choices remain open. No implementation or playtest is authorized. PM feedback recording does not resume the team.
db6396 Anonymous 2026-09-09 10:45:05
PM: resume team, record33 closure and499 submissions; adopt dated F1.14 forecast
26
aa4ad9 Anonymous 2026-09-08 15:40:03
Publish dated owner progress board
27
11b1cd Anonymous 2026-09-09 18:23:24
Record owner blockers, reopen readiness and simplify current PM status
28
Earlier reports and assessments remain in this page's revision history.