2026-09-06 22:29:50 66c091 Anonymous Archive/REV104: REV104 r4 (c3fc80) retained verbatim, superseded by REV104 r5
2026-09-06 22:25:37 008e1c Anonymous Archive/REV104: REV104 r3 (f7735a) retained verbatim, superseded by REV104 r4
2026-09-06 22:16:15 a46a72 Anonymous Archive/REV104: REV104 r2 (908e01) retained verbatim, superseded by REV104 r3
2026-09-06 21:50:27 f33b59 Anonymous Design Review/Archive/REV104 created: REV104 r1 (80a882) retained verbatim, superseded by REV104 r2
2026-09-06 19:47:47 80a882 Anonymous REV104 r1: first critique under PMU004 of WLD103 r19-r20 (campaign mystery thread, World r20): meets the mystery criteria in structure; five findings - REV104-1 what a local dispatch requires (drum/trunk/both; r18 vs r19, load-bearing), -2 collector vs clause 4, -3 delayed surge vs W1, -4 district circuit power source unstated, -5 routing bank = Finding 2 at campaign scale, 'dark' = Shut regime, price by rule. REV103 closed: -2/-7/-8 resolved in DD r14 (quoted), -9 resolved at World r18 (one %A711 mirror pending); three r5 pointers retracted as mid-rollout errors; r5 moved to Archive/REV103
2026-09-06 19:35:10 205bfb Anonymous REV103 r5: PMU004 applied - owner redirects scope to a multi-district campaign; one-district packet verdicts moot, rule-level findings become the shared rule contract; REV103-2/-7/-8/-9 re-labelled integration items (REV103-2 confirmed independently by EXT X27); REV104 criteria for DES104 pre-registered (shared rule contract first, Expansion Brief's six per district, campaign checks, ledgers + shared-rule diff); three PM pointers (Expansion Prompts 404, four index pages 404, Hub/Tasks still one-district); r4 moved to Archive/REV103
2026-09-06 19:25:38 711ef4 Anonymous REV103 r4: review of DES103 r7 (Design Document r13, 50046f) and World r17 (26f497); REV103-6 resolved (one arrival/stun/burst sequence, quoted), -7 resolved on the world page with %A711 lacking only the weir clause, -8 half resolved (%A71 'can reach'; stale PM-report sentence remains); REV103-2 residual unchanged (predates r3; 9/9 under most-room rule); new REV103-9: relay's channel energised or flowing decides whether opening the valves lights the yard; verdict revise, one kill, one clause, one sentence, one deletion; r3 moved to Archive/REV103
2026-09-06 19:16:25 dcd90e Anonymous REV103 r3: review of DES103 r6 (Design Document r12, 50840d) against PMR003; REV103-1, -5 resolved (corrections quoted); REV103-2 rule fixed but scene still off by one unit at the discharge threshold (9/9 not 10/8 under most-room rule); REV103-6 stun/arrival/burst timing (PMR003 1d), -7 finale valves/supply/coil-route crowds/workshop (PMR003 2, world page first), -8 stale wording (PMR003 3); r12 routing-split statement checked and accurate; verdict revise; r2 moved to Archive/REV103
2026-09-06 19:04:50 3ff337 Anonymous REV103 r2: review of DES103 r4 (Design Document r10, 8afa59); REV103-3 and -4 resolved in r10; REV103-1 open (%A712 leftover sentence, ledger cells); REV103-2 open and now load-bearing (collection rule defeats r10's storage battery); REV103-5 new (licences as interchangeable vs adaptation route, Clarity Q41 verified); r10's two new racks checked leak-free; verdict revise, three sentences and two ledger cells; r1 moved to Archive/REV103
2026-09-06 18:57:35 285925 Anonymous REV103 r1: present-tense review of DES103 r3 (Design Document r9, fb6b6d) on per-beat ledgers rebuilt from the rules; PMR002 1, 2, 4 met on the page, 3 met on World r16 but not yet lifted; verdict revise, one short pass: REV103-1 %A712 leftover sentence and two ledger cells, -2 collection rule disobeyed by both scenes, -3 %A711 Fix ending contradicts World r16 and %A74's two-cable model, -4 three stale sentences; REV102-13 resolved; REV102 r6 moved to Archive/REV102
2026-09-06 18:46:18 538724 Anonymous REV102 r6: closing correction - PMR002 declined the r2/r3 ready verdicts and is right; findings 1a-1d, 2a-2c, 3 verified against Design Document r8 in the present tense (%A71 yard-stays-dark vs shared circuit, %A78 nearest-beacon, %A712 seven slots, %A713 third bundle, hours arithmetic); ready verdicts withdrawn; r8 fixes REV102-10..12 verified, -13 open; REV103 acknowledged blocked; per-beat ledger method for REV103; r5 moved to Archive/REV102
2026-09-06 18:36:13 e2db8b Anonymous REV102 r5: critique of DES103 r1 (document r7, 44984c); criteria 1-11 met in structure, REV102-7..9 resolved; verdict revise, one bounded pass on the arc: REV102-13 arc undrawn/unplayed/link cost unstated (priority), -12 arc bound contradicts stated rates (EXT X22 verified), -11 electrician loop pays only with two batteries (EXT X22 verified), -10 'fills a battery' vs one unit (EXT X21 verified); r4 moved to Archive/REV102
2026-09-06 18:25:07 041852 Anonymous REV102 r4: PMU002 applied (D016 confirms baseline, D018 criterion 11 added to checklist, D015 contributors are teammates); Design Document r6 (12779d) assessed - rules unchanged; three items for DES103: REV102-7 cable pair named twice in Appendix A, REV102-8 decision 4's unsupported playtime inference per PMU002 X19 ruling, REV102-9 replace 'nine rounds certifies' per PM; r3 moved to Archive/REV102
2026-09-06 18:15:07 382607 Anonymous REV102 r3: confirmation on Design Document r5 (bc134b); REV102-6 resolved as recommended, mote count and section 8 lesson fixed in r4, owner summary accurate and code-free; verdict stands, DES102 r5 is the DES103 base; REV102 complete pending PM acceptance; REV102 rounds now archive at Archive/REV102 per editor suggestion
2026-09-06 18:06:03 82a96b Anonymous REV102 r2: re-review Design Document draft r3 (d35209); all five REV102 r1 issues verified resolved by section; verdict ready for owner review as DES103 base; one residual REV102-6 (what opens the junction gate); TRL101 C1 answered with four wrong sentences on record and one signed taste judgment; REV102 r1 moved to Archive
2026-09-06 17:59:37 4dde90 Anonymous REV102 r1: independent critique of Design Document draft r2 (c4ad51); verdict revise, one bounded pass then owner packet; five issues: tier-two gate open by default and pages crossed (adopt WLD r10 map), tier-three key is an item gate, coil-lit vs panel-lit beacon invisible (Q32), culvert joins one dock or two, withdrawal press bound unstated; EXT102 X10/X11 conceded as timing, X13 answered by r2; REV101 r8 moved to Archive
2026-09-06 17:48:35 11bd4d Anonymous REV101 r8: post-acceptance note - REV101 accepted (PMR001), REV102 assigned blocked on DES102; live verdict restated; Finding 2 closed under both routing models (r7 sight-limited, r8 district-wide), recommend confirming D013 with r8's relay/lamp separation; N16/N17 updates; EXT101 treated as data, X2/X3/X4/X6 document parts carried into REV102, X8 answered; r7 moved to Archive
2026-09-06 17:38:01 bb6871 Anonymous REV101 r7: re-review Design r4/r5 (42f653, b030c9) and WLD101 r7 (fa3eb1); N12-N15 resolved (beacon-sight rule, both pages), Finding 2 closed again, N11 reading reversed and re-checked; N17 added (surge-split rule: stale coil sentence, unplaced valve); editor split verified byte for byte and current+archive convention adopted; r6 moved to Archive; index updated
2026-09-06 17:30:35 a4b2eb Anonymous Split: move REV101 r5-r1 to the Design Review/Archive sub-page (verbatim, unedited) and leave the current review r6 here. 76 KB -> 19 KB, so the live verdict is the first thing on the page instead of the last. Adds a finding index mapping Findings 1-5, Secondary 1-5 and N1-N16 to where each now lives, so existing citations still resolve in one click. No review text was reworded.
2026-09-06 17:26:22 a89227 Anonymous REV101 r6: re-review Design r3 (0b4039) and WLD101 r5/r6 (430206); N10, N11, extraction trace, readability resolved; Q22 verified as load-bearing contradiction (N12: W2/cost(3)/does-not-turn-back vs continuous path; Finding 2 conditionally re-opened); Q23 verified (N13); N14 pump upkeep fiction vs rules; N15, N16; verdict unchanged; r5-r1 retained
2026-09-06 17:14:43 d3679b Anonymous REV101 r5: note on Hub PM-review policy (75c3c3) and outside-reader Clarity Questions (cc0ee7); Q18 verified as unstated case not contradiction (N11); Q17 constraint released; Q1-Q14 classified as DES102 criteria; verdict unchanged with scope explicit; r4-r1 retained
2026-09-06 17:04:27 3fd6df Anonymous REV101 r4: closing addendum for WLD101 r4 (e54d6a) and DES101 note 3 (db8c5c); N1-N4, N7-N9 resolved; N10 added (pulsing vs energised in W1 path clause); concept-packet review complete pending OWN101; next review is DES102; r3/r2/r1 retained
2026-09-06 16:55:25 698c13 Anonymous REV101 r3: addendum for WLD101 r3 (c92838) and DES101 note 2 (ea4248); N1 mostly resolved, N5/N6/S5 closed, N2/N3/N4 open, N7-N9 added; verdict unchanged, ready for OWN101; r2 and r1 retained
2026-09-06 16:51:49 47d51d Anonymous REV101 r2: re-review DES101 r2 (c9b2ed) and WLD101 r2 (438f1b); Findings 1-4, S1, S2, S4 resolved; S3 withdrawn (changelog is UTC+3); six DES102 carry-forwards; verdict ready for OWN101 concept steering; r1 retained
2026-09-06 16:27:42 7ad187 Anonymous REV101 r1: acknowledge role and design-only gate; review DES101 r1 (c340f6/4343a2) and WLD101 r1 (01378d); verdict revise before OWN101 with five findings