# Hold The Horde — Design Coverage
2
3
**PM coverage assessment, 8 September 2026.** This is the remaining-work map for the [whole-game outline](/Hold%20The%20Flood/Whole%20Game%20Outline), alongside the dated [Progress and forecast](/Hold%20The%20Flood/Progress). It is management work, not an additional completed gameplay package.
4
87e085 Anonymous 2026-09-08 19:48:02
Record combat completion, home review and dated milestone forecast
5
Across fifteen major areas, **nine have usable first-pass contracts and six have examples or alternatives**. These are coverage categories, not weighted progress or a percentage of the game. Even an area with usable rules still needs its finite content, edge cases and integration. “Written” does not mean owner-approved, implemented or validated.
c54276 Anonymous 2026-09-08 18:22:43
Record State and Production closeouts, regional review, and aligned v1 scope forecast
6
87e085 Anonymous 2026-09-08 19:48:02
Record combat completion, home review and dated milestone forecast
7
Six domains remain partial, and accepted rules still need their finite inventories and integration before v1 is complete. The newly usable category is Enemies, encounters and traps: Combat And Enemy Roster27 supplies the complete proposed roster and shared pressure/state contract alongside the existing trap families. Combat and contested work was already counted usable, so it is not counted twice. This classification does not complete the40-room, ten-encounter or twelve-mechanism inventories.
3e6459 Anonymous 2026-09-08 17:27:28
Publish PM whole-design coverage and remaining deliverables
8
9
The first complete wiki must describe actual behavior, progression and consequences across every major area. It may use clearly labelled provisional defaults and numerical tuning; a major area left only as “TBD” does not qualify. The later detailed-content milestone specifies the individual authored rooms, clues, encounters and scenes.
10
11
## Remaining first-pass work
12
13
SMALL below is the outline's proposed planning sample, not an adopted game size. Counts help expose work and may change after the scope decision.
14
15
| Area | Coverage now | Concrete remaining v1 outcome | Dependency and work that can proceed |
16
|---|---|---|---|
6b1d19 Anonymous 2026-09-08 18:49:25
Record regional closeout and acquisition review
17
| Expedition progression and regions | Partial: [Regional Discovery Map25](/Hold%20The%20Flood/Regional%20Discovery%20Map) prepared426 at3acda018, alongside the selected opening and outline | Twenty-four module and40placed-room v1 briefs linked to the prepared four-region/twelve-objective dependency map: proposed geometry/interfaces, actual contents, discovery/revisit purpose and access/recovery constraints; exhaustive instance variants remain M4 | Objective map closed18:32 Jerusalem. Final counts, ending destinations and physical joins remain replaceable until selected; the regional domain is still partial. |
3e6459 Anonymous 2026-09-08 17:27:28
Publish PM whole-design coverage and remaining deliverables
18
| Death, shifts and station connections | Conditional [joining mechanism](/Hold%20The%20Flood/Connecting%20The%20Station) | One shared rule set for death order, room/object identity, permanent joins, recovery, rescue interaction and whole-station completion | Local permanence is already selected. The final-layout answer affects the rigid candidate; identity and recovery requirements can proceed now. |
19
| Oxygen, condition and carrying | Usable [first-pass rules](/Hold%20The%20Flood/Survival%20And%20Loadout) | Variant/edge-case matrix and provisional opening quantity sheet | No owner answer blocks paper variants. Pressure and balance need later authorized evidence. |
b4093e Anonymous 2026-09-08 19:11:20
Record acquisition closeout, combat roster work and revised coverage
20
| Connected-build grammar | Usable [first-pass rules](/Hold%20The%20Flood/Build%20Rules) | Conversion, storage, saturation, readiness and rig/infrastructure conformance matrix | Narrow04 parent alignment integrated432 atb7b70875/42a0be59/2d6de3c0; PM retains STOPPED ownership of all three parents. Exact geometry/quantities may remain provisional; global rules, integration and pending owner choices remain open in04. |
21
| Equipment and acquisition | Usable twelve-part [catalogue](/Hold%20The%20Flood/Equipment%20Catalogue) and [acquisition/growth contract26](/Hold%20The%20Flood/Equipment%20Acquisition%20And%20Rig%20Growth), prepared434 atf5f6d768 | Source-fixture briefs and exception/recovery details, with concrete exemplar/port/material/source paths before any repair/adapter template becomes a usable route; provisional quantities and geometry | Closed18:57:01 Jerusalem after one focused critique/response and PM maintenance. All twelve paths, four starters/eight sources, three added fixtures and legal rig/property costs are prepared. The domain is not finished; acquisition preference and actual starter/capacity choices remain unselected. |
87e085 Anonymous 2026-09-08 19:48:02
Record combat completion, home review and dated milestone forecast
22
| Combat and contested work | Usable [Combat Rules](/Hold%20The%20Flood/Combat%20Rules) and [combat-state contract27](/Hold%20The%20Flood/Combat%20And%20Enemy%20Roster), prepared443 | Remaining interface/edge-case matrix for controllers, target assistance, combined attacks, oxygen actions and recovery | Shared first-pass state sheet prepared19:34 atf1fe0d9a. Target assistance, multiple ordinary controllers and field healing remain proposals; exact timing and readability are unvalidated. |
23
| Enemies, encounters and traps | Usable [roster/pressure contract27](/Hold%20The%20Flood/Combat%20And%20Enemy%20Roster), prepared443, alongside five [trap families](/Hold%20The%20Flood/Traps%20And%20Encounter%20Progression) | Ten encounter-placement and twelve placed-mechanism v1 briefs: actual geometry/populations, cue variants, warning/work stages, reset/rearm/persistence and recovery; exhaustive variants remain M4 | Six ordinary/three special roles and two setpieces are prepared within ten encounters; ten of twelve mechanism slots allocated. Full inventories are still partial, and counts/origins remain replaceable proposals. |
3e6459 Anonymous 2026-09-08 17:27:28
Publish PM whole-design coverage and remaining deliverables
24
| Two alien languages and discovery | [Expedition example](/Hold%20The%20Flood/Language%20Expedition), journal rules, [testable interaction](/Hold%20The%20Flood/Alien%20Utterance%20Discovery) | Four SMALL discovery chains across both languages: evidence, competing interpretations, discriminating action, correction and later use | Draft operational chains now. Define how visitor marks and utterance registers relate; a response alone does not prove request semantics or a god. |
25
| Story, endings and corruption | [Story](/Hold%20The%20Flood/Hospital%20Story%20Directions) and [corruption alternatives](/Hold%20The%20Flood/Resurrection%20And%20Corruption) | Beat/evidence/consequence map through apparent, deeper and optional secret layers, including visible ending choices and colony consequences | Final canon needs owner choices. Draft the causal alternatives now; no automatic death budget, ending lock or mandatory treatment. |
26
| Authored cast and short rescue | Two [first-survivor alternatives](/Hold%20The%20Flood/First%20Survivor) and local examples | Five SMALL cast briefs: motives, disagreements, bounded knowledge, home contribution, three-scene arc and short rescue outcomes | The first-survivor choice and global mortality affect specific branches. Other characters and living crossings can proceed. |
87e085 Anonymous 2026-09-08 19:48:02
Record combat completion, home review and dated milestone forecast
27
| Colony and home projects | Partial: [Coming Home](/Hold%20The%20Flood/Coming%20Home), [Home Projects](/Hold%20The%20Flood/Home%20Projects); [Home And Colony Loop28](/Hold%20The%20Flood/Home%20And%20Colony%20Loop) submitted446, review447 active | Living/death return and preparation contract plus five person-linked projects with voluntary contributions, concrete operation, reclaim and postponement; two reused/three new | Systems STOPPED after submission446 at19:42:37, source1b2eefba; independent review447 active against criteria registered445. Draft20:20 target achieved early; reviewed21:15(20:45–22:00) remains forecast, today8Sep Jerusalem. Final five cast arcs/15scenes, person selection and any management economy remain separate. |
3e6459 Anonymous 2026-09-08 17:27:28
Publish PM whole-design coverage and remaining deliverables
28
| Information, controls and accessibility | Usable [first-pass contract](/Hold%20The%20Flood/Player%20Information) | Cue/interaction inventory, journal/manifest structure and option/default interactions, including non-colour/non-audio equivalents | Most work can proceed. Mechanical uncertainties affect their particular displays. Full journal pause is settled. Existing article ownership must be respected. |
cde85a Anonymous 2026-09-08 18:21:01
Clarify v1 room and mechanism brief obligations and uniquely account for their remaining work
29
| Save, identity and content authoring | Usable [first-pass contract](/Hold%20The%20Flood/Save%20And%20Content%20State), preparation-closed417 at438cdf35 | Complete transition/commit catalogue, placement/reference matrix and resolved conditional branches and recovery policy | First-pass identity/continuity requirements are prepared. Save policy, rescue/shift order and full-station behavior remain open; engineering/migrations remain later. |
c54276 Anonymous 2026-09-08 18:22:43
Record State and Production closeouts, regional review, and aligned v1 scope forecast
30
| Content scope and production feasibility | Usable [first-pass scope contract](/Hold%20The%20Flood/Production%20Scope), prepared423 atc1a60388 | Deduplicated finite inventory, reuse assumptions, unique authoring/state costs, asset categories, Unity/Steam constraints and explicit scope cuts | PM24 closed423;144–247role-hourv1 planning allowance with explicit room/mechanism depth. Scope/band/cuts remain proposed; actual asset licences/specifications need checking. |
4a0912 Anonymous 2026-09-08 17:54:20
Record trap/handoff closeouts and active save-state design
31
| Development and validation handoff | Usable [first-pass plan](/Hold%20The%20Flood/Development%20And%20Validation%20Handoff), prepared410 | Final v1-specific packet with exact revisions, development scope, conditions, staffing, estimates and decision criteria | Eleven risks/gates are mapped, including sustained progression. Actual prototypes, code, simulations, assets and playtests require explicit phase authorization. |
3e6459 Anonymous 2026-09-08 17:27:28
Publish PM whole-design coverage and remaining deliverables
32
33
## Work sequence and forecast
34
35
| Window, Jerusalem dates | Planned result | Staffing/dependency |
36
|---|---|---|
87e085 Anonymous 2026-09-08 19:48:02
Record combat completion, home review and dated milestone forecast
37
| 8 Sep | Prior system contracts and Combat27 prepared443; narrow04 parent-equipment and legacy integration complete; Home28 submitted446 | PM and GPT review work continues; Systems STOPPED after Home28 submission19:42:37, with one focused independent review447 active. Both original Claude roles stay paused; specialist setup9–10Sep remains planned, not active. |
3e6459 Anonymous 2026-09-08 17:27:28
Publish PM whole-design coverage and remaining deliverables
38
| 9–11 Sep, core buffer to 14 Sep | Shared core rules and identity requirements; start region, cast, language and production work | Two additional specialist setups planned 9–10 Sep. Ready scopes, not provider availability alone, determine assignments. |
39
| 14–18 Sep | Domain designs and finite inventories sufficiently concrete for cross-domain review | Content counts and major story/mechanism choices must be dispositioned or visibly provisional. |
40
| Target 22 Sep; likely 18–29 Sep | Complete first-pass wiki with integrated interfaces and a development handoff outline | PM integration and review are on the critical path; more writers do not remove that work. |
41
| Target 10 Nov; likely 20 Oct–1 Dec | Detailed finite authored campaign specification | Low-confidence estimate until an inventory and representative detailed packages are checked. |
42
43
The core target remains **11 September (10–14 September)**. These are planning estimates, not guarantees or demonstrated playtime. The next substantive re-estimate is **9 September at 18:00 Jerusalem**. Early completion of a local written package does not by itself justify bringing the whole-wiki date forward.
44
87e085 Anonymous 2026-09-08 19:48:02
Record combat completion, home review and dated milestone forecast
45
Shared integration outcome04’s narrow parent-equipment alignment432 and legacy Discovery Chain/Expedition slice441–443 are complete. The latter replaces stale route/journal clauses in those two bodies, with no new access guarantee. Remaining global shift/rescue/full-station branches and other affected articles still need integration;04 stays open. A pending choice blocks only the rules that actually depend on it, not every parallel stream.
3e6459 Anonymous 2026-09-08 17:27:28
Publish PM whole-design coverage and remaining deliverables
46
47
## Estimate accounting
48
49
The outline's **111–208 role-hours is a partial original specification allowance, not remaining labor**. Its survival and information first-pass packages are now prepared. The later survival22–39 and information35–59 role-hour envelopes describe deeper inventories; they are not measurements of elapsed effort and must not simply be added to the old total. Equipment's first-pass allowance likewise differs from its later detailed catalogue.
50
87e085 Anonymous 2026-09-08 19:48:02
Record combat completion, home review and dated milestone forecast
51
Track deliverable and depth separately: first-pass rule set, finite content inventory, and later implementation. Count a shared survivor scene/colony project/clue/region objective once, then estimate only its distinct additional work. Keep package review/response, PM cross-page integration and whole-game coherence review separate without double counting. Production24's response explicitly assigns the24module/40room/12mechanism v1 brief minimums to one20–34author-hour package, beyond objective allocation. This retains the placed-mechanism obligation rather than silently deferring it. Detailed campaign authoring extends these briefs; do not charge both full depths. See [Production Scope](/Hold%20The%20Flood/Production%20Scope) for the proposed revised144–247role-hour v1 allowance and separate review/response/integration; it is the dated8Sep planning estimate, not logged labor or an automatically current remaining balance; subtract accepted scope before recomputing the remainder.
3e6459 Anonymous 2026-09-08 17:27:28
Publish PM whole-design coverage and remaining deliverables
52
87e085 Anonymous 2026-09-08 19:48:02
Record combat completion, home review and dated milestone forecast
53
This map is based on the current owner brief, Whole Game Outline revised through narrow alignment432 at2d6de3c0, the linked owning articles and a source-by-source PM coverage audit. The catalogue was subsequently read at submission396, received one focused review/response397/399 and was preparation-closed400 at revision737b3cfd. Outcome21 trap/encounter and22 handoff first passes were closed410;23 save/content-state closed417 at18:09:56 Jerusalem, final438cdf35. Production24 closed423 after scoped response421/422; Regional Discovery Map25 closed426 after response425 at3acda018. Its objective map leaves the domain partial pending24module/40room briefs. Acquisition26 closed434 at18:57:01, finalf5f6d768, after actual429, one focused critique431, the verified author response and PM’s paragraph-only maintenance433. Late notice436 records pre-maintenancef7ede725 rather than a rollback. PM now classifies equipment/acquisition as a usable first-pass contract, with source-fixture detail and exceptions still required. Combat And Enemy Roster27 closed443 at19:34, finalf1fe0d9a, after one focused critique and the442 response. PM now classifies the existing enemy/encounter/trap category as usable first-pass; the already usable combat category is not counted again. Exact40room/ten-encounter/twelve-mechanism inventories remain incomplete. Home And Colony Loop28 was submitted446 at19:42:37, source1b2eefba, with pre-assignment criteriabb3b76f3 registered445; one independent review447 is active and Systems STOPPED. Submission is not a prepared home contract. Narrow legacy04 Discovery114e9267/Expedition836ab2ae integration is verified443; global04 remains open. Scope estimates are reviewed planning assumptions, not validated labor or adopted content counts. The separately found Rescue Shift Proposal and Station Assembly Example remain unadopted intake407, not completed shared integration. The management checkpoint retains the exact inspected source revisions. No page count, model agreement or desk review establishes fun, balance, usability, performance or campaign duration.