Commit 16dda9

2026-09-08 18:49:23 Anonymous: Record regional closeout and acquisition review
hold the flood/progress.md ..
@@ 1,12 1,12 @@
# Hold The Horde — Progress
- **Updated 2026-09-08 18:26 Jerusalem (UTC+3).** PM and GPT work continues; only the two Claude roles are paused. All work remains **design only**.
+ **Updated 2026-09-08 18:49 Jerusalem (UTC+3).** PM and GPT work continues; only the two Claude roles are paused. All work remains **design only**.
- **25 tracked design packages: 23 preparation-closed, 2 open.** Save And Content State23 closed417 at18:09:56 Jerusalem. Production Scope24 then closed423 at18:21. Regional Discovery Map25, assigned418, is in author response424 after review of draft420; shared integration04 remains dependent. The separate management coverage map and two unadopted intake contributions are not extra completed packages. These are bounded written outcomes, not overall game completion.
+ **26 tracked design packages: 24 preparation-closed, 2 open.** Regional Discovery Map25 closed426 at18:32 Jerusalem after its one focused review/response. Equipment Acquisition And Rig Growth26 draft429 arrived18:42:21 and is in focused independent review; Systems is stopped awaiting critique. PM completed the narrow parent-equipment compatibility audit for04 and is preparing exact local alignment drafts; publication/integration and owner-dependent global branches remain open. The separate coverage map and unadopted intake407 contributions are not extra completed packages. These are bounded written outcomes, not overall game completion.
“Closed” means the bounded written design/review outcome is complete. It does not mean a feature is implemented, every detail approved or fun validated. This board covers the current design batch; it is not a complete campaign or production backlog, and the closed/total ratio is not an overall game-completion percentage. Stable IDs stay fixed; added/reopened work must be recorded explicitly.
- **Availability correction —8 Sep:** only Claude is paused. PM and the existing GPT Systems designer continue useful work with bounded independent GPT reviews. Production24 is preparation-closed423; Regional25's focused review is complete and Systems is revising under424. PM will verify its final response while handling intake and forecasts. Neither permanent Claude role will be woken or replaced before owner confirmation. Active one-minute fallback monitoring and15-minute progress/forecast reports continue.
+ **Availability correction —8 Sep:** only Claude is paused. PM and the existing GPT Systems designer continue useful work with bounded independent GPT reviews. Systems submitted Acquisition26 as429 and stopped; the independent reviewer is active on actual58ea915a using the previously saved criteria. PM has completed04’s read-only parent-equipment audit and is preparing targeted local alignment drafts for publication. Neither permanent Claude role will be woken or replaced before owner confirmation. Active one-minute fallback monitoring and15-minute progress/forecast reports continue.
## Forward forecast — baseline F1
@@ 43,7 43,7 @@
The critical sequence is core decisions and interfaces → whole-game architecture/content budget → domain designs → cross-domain integration → v1. Content detail proceeds in parallel only where interfaces are stable. Extra writers do not eliminate the PM/review bottleneck.
- **Next delivery, today Jerusalem:** [Regional Discovery Map25](/Hold%20The%20Flood/Regional%20Discovery%20Map) draft arrived18:16 (target18:45); reviewed target19:30(range19:00–20:00). [Production Scope24](/Hold%20The%20Flood/Production%20Scope) closed18:21 (target19:40), and Save And Content State23 closed18:09:56 (target19:00). Core11 Sep(10–14), complete first-pass wiki22 Sep(18–29), and specialist setup9–10 Sep remain unchanged. The revised144–247role-hourv1 allowance needs the9Sep capacity check; if both additional streams are absent10Sep, the provisional current-team scenario is25Sep(22Sep–2Oct).
+ **Next delivery, today Jerusalem:** [Equipment Acquisition And Rig Growth26](/Hold%20The%20Flood/Equipment%20Acquisition%20And%20Rig%20Growth) draft arrived18:42:21 against its19:00 target(range18:45–19:20); focused review is active, with reviewed outcome19:45(range19:15–20:15) unchanged. [Regional Discovery Map25](/Hold%20The%20Flood/Regional%20Discovery%20Map) closed18:32 against its19:30 reviewed target. Production24 closed18:21 (target19:40), and Save And Content State23 closed18:09:56 (target19:00). Core11 Sep(10–14), complete first-pass wiki22 Sep(18–29), and specialist setup9–10 Sep remain unchanged. The144–247role-hourv1 allowance needs the9Sep capacity check; if both additional streams are absent10Sep, the provisional current-team scenario is25Sep(22Sep–2Oct).
## Extra agents — when and why
@@ 78,14 78,15 @@
|F1.4|8 Sep17:54|Traps21 and Handoff22 actual17:48 recorded against18:45/18:15 targets. Next Save And Content State23 reviewed target19:00(18:30–19:30). M2–M4 unchanged: full campaign, content inventory and integration still require work.|
|F1.5|8 Sep18:09:56|State23 actual closeout417 recorded against its19:00 reviewed target. New418 outcomes: Regional Map25 reviewed19:30(19:00–20:00), Production Scope24 reviewed19:40(19:05–20:10). M2–M4 unchanged pending reviewed remaining-scope accounting; a Production draft is not a reviewed forecast.|
|F1.6|8 Sep18:21|Production24 closed423. Its reviewed response exposes previously unallocated v1 room/mechanism briefs:144–247role-hours replaces draft116–201. M2–M4 dates retained provisionally;9Sep re-estimate must check capacity. If extra streams are unavailable10Sep, current-teamv1 scenario25Sep(22Sep–2Oct). Regional25 reviewing420, target19:30.|
+ |F1.7|8 Sep18:32|Regional25 actual closeout426 recorded against its19:30 reviewed target. New Acquisition26 assignment427 targets draft19:00(18:45–19:20), reviewed19:45(19:15–20:15). M2–M4, the F1.6 planning allowance and current-team scenario remain unchanged; accepting a regional map does not complete its room inventory.|
## What changed in this report
- - [Save And Content State23](/Hold%20The%20Flood/Save%20And%20Content%20State) preparation-closed417 at18:09:56, final438cdf35. The returning manifest includes active rig and inactive cargo once; delivery requires the same person aboard and the closed airlock; saved evidence retains provenance without refreshed truth. Save policy and unresolved rescue/shift behavior remain proposals.
- - New [Production Scope24](/Hold%20The%20Flood/Production%20Scope) gives PM the finite scope/reuse/cost comparison. New [Regional Discovery Map25](/Hold%20The%20Flood/Regional%20Discovery%20Map) gives Systems four proposed regions and twelve linked objectives. Production24 closed423 at18:21 after its one review/response; Regional25 draft420 at18:16 received one independent review; Systems is responding under424, then PM verifies the final source.
- - The [coverage map](/Hold%20The%20Flood/Design%20Coverage) now distinguishes seven first-pass contracts and eight partial areas. The regional map remains partial; no overall percentage is implied.
- - Intake407 remains open: Rescue Shift Proposal and Station Assembly Example are unadopted, with contributor/ownership context and consequential choices pending. Neither answers the existing owner questions or closes04.
- - Production review exposed missing explicit room/mechanism authoring. The revised144–247role-hourv1 allowance includes24module/40room/12mechanism brief minimums and unique review/response/integration. It is a planning estimate, not recorded effort. Both Claude roles remain paused; dates stay provisional pending9Sep capacity review.
+ - [Regional Discovery Map25](/Hold%20The%20Flood/Regional%20Discovery%20Map) preparation-closed426 at18:32, final3acda018. Five earlier A/B occurrences and three address comparisons now support both proposed orders; a concrete pressure iris, visible failed prediction and slower alternative replace the abstract central gate. The calibration compares the same astronaut, and the later rig/source/access costs are explicit.
+ - [Equipment Acquisition And Rig Growth26](/Hold%20The%20Flood/Equipment%20Acquisition%20And%20Rig%20Growth) draft429 arrived18:42:21, submitted source58ea915a,26,193bytes. It proposes twelve part sources, reversible active-area growth, legal alternatives and property lifecycle. Systems is stopped; the independent reviewer is now active against criteria saved before the draft. Its recommendations remain unreviewed until the critique/response and PM disposition.
+ - PM completed04’s narrow read-only parent-equipment compatibility audit; the full report174b4132 was read. Exact local parent-alignment drafts are being prepared for PM publication. This is targeted integration work, not a broad second review or a closed global station contract. Owner-dependent shift/rescue/full-station branches remain open.
+ - The [coverage map](/Hold%20The%20Flood/Design%20Coverage) remains seven first-pass contracts and eight partial areas. Regional objectives are prepared, but24module/40room v1 briefs still remain. No overall percentage is implied.
+ - Intake407 remains open and unadopted. Both owner questions and the Claude-only pause are preserved. M2–M4 and the F1.6 current-team scenario stay unchanged pending9Sep capacity review;144–247role-hours remains a planning allowance, not recorded effort.
## Open and closed outcomes
@@ 96,7 97,7 @@
|01|[Reusable equipment combinations](/Hold%20The%20Flood/Build%20Rules)|Closed|Selected direction|Sep7 22:19; updated Sep8 13:45|Catalogue and numerical rules remain proposed|
|02|[Oxygen visibility and journal pause](/Hold%20The%20Flood/Oxygen%20and%20Observation)|Closed|Selected direction|Sep7 20:55; updated Sep8 13:45|Exact oxygen amounts remain open|
|03|[Carried property returns on death](/Hold%20The%20Flood/Death%20And%20Persistence)|Closed|Selected rule|Sep8 13:45|Shift and survivor ordering tracked separately|
- |04|[Shifts, persistent work and historical records](/Hold%20The%20Flood/Shifting%20Station%20Options)|Open — dependent|Binding direction selected|Sep8 14:49 direction recorded|Integrate final station contract after15; older fixed-map clauses are superseded|
+ |04|[Shifts, persistent work and historical records](/Hold%20The%20Flood/Shifting%20Station%20Options)|Open — alignment drafting|Binding direction selected|Sep8 narrow PM compatibility audit complete|Exact local parent-equipment alignment drafts in preparation; PM publication/integration pending. Owner-dependent shift/rescue/full-station branches remain open|
|05|[Ordinary combat and horde encounters](/Hold%20The%20Flood/Combat%20Rules)|Closed|Selected direction|Sep8 10:51; updated13:45|Automatic ordinary fire, manual specials; balance remains open|
|06|[First-survivor comparison](/Hold%20The%20Flood/First%20Survivor)|Closed|Short rescue selected; person unchosen|Sep8 response364/disposition368|Yeva versus Aster ready; short-route condition and death/refuge timing remain explicit limits|
|07|[Practical discovery and optional help](/Hold%20The%20Flood/Clues%20and%20Help)|Closed|Selected direction|Sep8 11:23; updated13:45|Current routes cannot be inferred from historical records|
@@ 117,7 118,8 @@
|22|[Development and validation handoff](/Hold%20The%20Flood/Development%20And%20Validation%20Handoff)|Closed|Reviewed first-pass risk/evidence plan|Sep8 17:48 disposition410|Final v1-specific scope, staffing and estimates precede any owner phase decision; no development authorized|
|23|[Save and content state](/Hold%20The%20Flood/Save%20And%20Content%20State)|Closed|Reviewed first-pass continuity contract; save policy unselected|Sep8 18:09:56 disposition417|Final438cdf35; detailed transitions, rescue/shift ordering, save-policy and recovery choices remain open|
|24|[Production scope](/Hold%20The%20Flood/Production%20Scope)|Closed|Reviewed provisional finite scope and work accounting|Sep8 18:21 disposition423|Finalc1a60388;144–247role-hourv1 planning allowance, not measured labor; band/cuts unselected|
- |25|[Regional discovery map](/Hold%20The%20Flood/Regional%20Discovery%20Map)|Open — author response|Four-region/twelve-objective SMALL planning proposal|Sep8 response assignment424|Fix gallery prerequisites, physical central gate and calibration evidence; response18:45(18:35–19:00), reviewed19:30(19–20)|
+ |25|[Regional discovery map](/Hold%20The%20Flood/Regional%20Discovery%20Map)|Closed|Reviewed four-region/twelve-objective SMALL planning proposal|Sep8 18:32 disposition426|Final3acda018;24module/40room v1 briefs, actual placements and owner story/ending choices remain open|
+ |26|[Equipment acquisition and rig growth](/Hold%20The%20Flood/Equipment%20Acquisition%20And%20Rig%20Growth)|Open — reviewing|Proposed sources and active-area growth; owner acquisition choice remains open|Sep8 18:42:21 draft429|Actual58ea915a; Systems stopped, independent reviewer active. Draft19:00 target achieved early; reviewed19:45(19:15–20:15) unchanged|
## Recent delivery timeline
@@ 137,14 139,15 @@
|Stream|Now|Next|
|---|---|---|
|Equipment catalogue|Preparation closed400; final737b3cfd|Use in trap/encounter examples; detailed controller and acquisition integration later|
- |Whole-v1 coverage|Fifteen-domain map updated after423: seven first-pass contracts and eight partial areas|Production24 establishes the costing/depth baseline; Regional Map25 advances a partial domain, while finite inventories still need authoring|
+ |Whole-v1 coverage|Fifteen-domain map remains seven first-pass contracts and eight partial areas|Regional25 prepares objective dependencies; module/room inventories and integration still need authoring|
|Trap/encounter progression|Preparation closed410; finala280131b|Use concrete family rules; detailed instances/roster later|
|Development handoff|Preparation closed410; finalc0c38e8b|Keep gates explicit; final handoff packet depends on concrete v1/development scope|
|Save/content state|Preparation closed417 at18:09:56; final438cdf35|Use explicit continuity interfaces; detailed state work and owner selections remain later|
|[Production Scope24](/Hold%20The%20Flood/Production%20Scope)|Preparation closed423 at18:21; finalc1a60388|Use144–247role-hour planning allowance with explicit v1/M4 depth and capacity limits|
- |[Regional Discovery Map25](/Hold%20The%20Flood/Regional%20Discovery%20Map)|Systems responding under424 after one focused critique|PM verify finalsource/dispositions; reviewed19:30(19:00–20:00)|
+ |[Regional Discovery Map25](/Hold%20The%20Flood/Regional%20Discovery%20Map)|Preparation closed426 at18:32; final3acda018|Use both revised orders and explicit evidence/access conditions; finite module/room briefs remain|
+ |[Equipment Acquisition And Rig Growth26](/Hold%20The%20Flood/Equipment%20Acquisition%20And%20Rig%20Growth)|Draft429 received18:42:21; Systems stopped, independent focused review active|One critique/response then PM disposition; reviewed19:45(19:15–20:15) unchanged|
|Additional proposal intake|Both full pages read; explicitly unadopted|Track authorship and assess protected retreat/next-shift meeting before integrating|
- |Shared integration04|Current owner rules known; some mechanisms/choices pending|Integrate confirmed rules and explicitly isolate unresolved decisions|
+ |Shared integration04|Narrow read-only parent-equipment audit complete; exact local alignment drafts being prepared|PM owns publication; owner-dependent global branches stay open. No broad review or integration completion claimed|
|Claude Lead/Reviewer|Paused by owner for token limits|Resume only when owner confirms; GPT work continues meanwhile|
|Specialist setup|Two bounded briefs ready|Planned9–10Sep; no new permanent sessions created|
0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9